SARTELL (WJON News) -- The Mill Site improvement project in Sartell suffered a minor setback on Monday. At Monday night's city council meeting the council voted to reject the bid for the utility work at the site.

98.1 Minnesota's New Country logo
Get our free mobile app

Bids were opened on September 17th and RL Larson Excavating, Inc. of St. Cloud was the low bidder at $2.025,575.19.. The bid was about $500,000 higher than the engineer's estimate of $1,515,397.50. When the city reviewed the bid it was determined that costs for concrete removal, clean-up, and earthwork were the factors contributing to the higher bid.

Image Credit: Google Maps
Image Credit: Google Maps
loading...

Staff recommended rejecting the bid so the city can revise the scope of the project over the next month and then open it back up for rebidding in November. The city anticipates awarding the contract before the end of the year and will also continue to pursue and apply for additional grants to help cover the redevelopment costs.


READ MORE FROM AUTHOR PAUL HABSTRITT:


 

These people from the St. Cloud area have competed at the Olympic Games

 

Come Visit St. Augusta, Minnesota in Pictures

 

Minnesota Area Codes as Work Shoes

More From 98.1 Minnesota's New Country